PPG China Conclude Transportation of Transformers from Hong Kong to Substation Site in Macau





Cargo details:
1.
Transformers & Reactors
-
4 Units x 10.4(L) x 3.45(W) x 3.95 (H), 187 tonnes / total 748 tonnes
-
2 Units x 6.4(L) x 3.3(W) x 4.2 (H), 82 tonnes / total 164 tonnes
2.
Accessories
-
213 Crates / Total 1,700CBM
Scopes of work:
-
Cargo receiving from mother vessel in Hong Kong and deliver to Macau
-
Cargo lashing, space arrangement of feeder vessels
-
Equipment mobilization includes feeder vessels, floating crane barge, SPMT, heavy trailers
-
Port and import / export formality in Macau
-
Transformers and reactors loaded by floating crane barge onto the SPMT at Macau port
-
Mid-night delivery (SPMT) from Macau port to jobsite with police escort
-
Unload and position of transformers by hydraulic jacking system and turning table
-
Final shifting for 187t and 82t without crane, within 1cm allowance
For such remarkable project ever in Macau – the heaviest transformers to be delivered, Wangfoong project team spent more than a year in planning from logistics engineering to final operation. Under COVID-19, numerous challenging factors included quarantine for project crews, equipment mobilization with import and export formalities, overcoming site restrictions, closely working with clients at the site, and unexpected delay of mother vessel in final port, which finally we manage all issues under control and deliver the transformers and reactors on time. We appreciate all the supports from management, our crews, clients and different local authorities.